| Construction
of Cinema theatres/Multiplexes |
| |
|
1.
Ans : |
I
plan to construct a cinema theatre/multiplex. What is the procedure for it?
First you have to obtain NOC for the location of the proposed construction from
The Office Of The Commissioner Of Police |
2.
Ans : |
What should I do to have such NOC ?
You have to make an application affixing court fees stamp of Rs. 5/- along with following necessary documents.
1. Plan of the proposed site indicating surroundings,
roads and buildings up to a
distance of 75 meters from
the perimeter. Schools, hospitals, temples or other
similar places should be clearly indicated in the plan
along with floor wise
plans (3 sets)
2. Certificate from the Collector for N.A. land.
3. Property card
4. Appointment letter of the architect.
5. Agreement between land Owner and Builder/Developer or Power of Attorney.
6. Copies of applications submitted to PWD and Buildings Proposals
Department
along with their remarks |
3.
Ans : |
How much
time will it take?
It will take six months because :
1. Objections will be invited from members of public by displaying a board with
details of the proposal at the site and by publishing
the same in three local
news papers.
2. Enquiries will be conducted by the local Police station from the law and order
point of view.
3. A report will be invited from the traffic
department for Traffic point of view.
4. After completion of all the above procedure, the proposal will be submitted
to
the government for previous sanction.
5. After the receipt of previous sanction from the government, an NOC will be
issued. |
4.
Ans : |
When should I start the construction?
To commence construction, you will require an NOC from the office of the Commissioner of Police.You will have to make an application and submit the
following documents:
1. A true copy of the NOC issued by the licensing authority with respect
to the site
where the cinema is proposed to be put up.
2. Approved plans (by the Building Proposals Department, BMC)
3. IOD from the BMC
4. NOC from the Chief Fire officer, BMC
After receipt of the same, the papers will be processed and then NOC for construction will be issued. |
5.
Ans : |
How long
will it take?
It will take one month. |
|
6.
Ans :
|
After completing construction, how do I procure
a license to start the business?
After completing construction, you will have to
make an application for grant of license. You have
to submit the following documents along with your
application:
1. Occupation certificate from the BMC.
2. NOC from the Electrical Inspector.
3. NOC from the Health Officer, BMC.
4. Certificate from MTNL.
5. Certificate of lighting contractor.
6. NOC from the Chief Fire Officer, BMC.
7. NOC from the Traffic Police regarding parking.
8. NOC from PWD.
9. Structural stability certificate from the
architect.
10. Name and address of the Manager, Projector operator
and Electrician.
After the receipt of the same, the proposal will
be submitted to the Government for previous sanction.
After receipt of the previous sanction from the
Government, the license will be issued.
|
7.
Ans : |
How much time
will this process take?
The process will take minimum two month's time. |
8.
Ans : |
Under what law the license is required?
Maharashtra Cinema (Regulation) Rules, 1966 |
9.
Ans : |
What is the fee structure?
Fees
1. Cinema license
up to 200 seats Rs. 2,000
up to 500 seats Rs. 3,000
above 501 seats Rs. 4,500
2. Ticket selling license Rs. 300
3. Addition/alteration in the license Rs. 25
4. Duplicate license Rs. 50 |
10.
Ans : |
What is the procedure for renewal of license?
For renewal of the license, you will have to submit
the following documents along with the application:
1. NOC from PWD
2. NOC from the Electrical Inspector
3. NOC from the Health Officer, BMC
4. Certificate from MTNL
5. Certificate of lighting contractor
6. NOC from the Chief Fire Officer, BMC
7. NOC from the Traffic Police regarding parking
8. Certificate regarding screening of approved films
9. NOC from the Collector.
After the receipt of the same, enquiries will be
made through the local Police station and once the
report is received, the license will be renewed.
|
11.
Ans : |
What are the
charges for renewal?
Same as given in fee structure. |